The Coast Highway 101 bridge over the San Elijo Lagoon inlet has a sidewalk on each edge. The east sidewalk is the wider one, and City of Encinitas engineering documents describe it as ADA-compliant. The west sidewalk faces the ocean, gets more walkers, and is narrower, as The San Diego Union-Tribune reported in September.
The bridge has now been rated "poor," and federal money is lined up to fix it. Under that program, widening the ocean-side walkway counts as an improvement, and Encinitas would pay the whole cost of it. The decision about how wide that walkway gets is happening now, between the city and Caltrans, years before any construction crew shows up.
The bridge sits just south of the San Elijo State Beach campground. It was built in 1934 and widened on its western side in 1953. Today it carries two vehicle lanes in each direction, a protected bike lane in each direction, and a pedestrian walkway on each edge. The city's 2026 assessment counts about 20,300 average daily trips across it.
It has needed repeated repairs. A March 2026 city staff report lists repair work on the bridge piers in the 1990s and emergency work in 2019 to patch areas where concrete was delaminating on the underside of the deck. It also notes that Caltrans structural engineers inspect the bridge regularly, most recently in 2024. In August 2022 the City Council hired Shaw Equipment Rentals for a not-to-exceed $322,453 job covering backfill, crack and pavement repair, abutment sealing and guardrail replacement. That work began November 1, 2022, wrapped up around December 23, and the council accepted it on January 25, 2023.
All of those were patches. The larger rehabilitation is the first project in decades that could change the bridge's layout. It is also the point where the two walkways could stop being so different.
This January, the city hired Kleinfelder, Inc. to assess all 46 bridges it owns or maintains and to draft a 10-year repair plan. Inspectors did hands-on inspections during the week of April 6, according to The Coast News. Only two structures came back rated poor. One is the Highway 101 bridge over the lagoon. The other is the westernmost pedestrian bridge at Leucadia Oaks Park.
The Union-Tribune reported that the lagoon bridge shows chipped concrete and rusting rebar. Kleinfelder engineer Kelly Burnell told the council that "poor doesn't mean unsafe." The Coast News reported her fuller explanation:
"Poor means that some of the primary components of the bridge – whether it's a column or a girder – is starting to show signs of deterioration. And that deterioration is not yet affecting the ability of the bridge to perform, but it might in the future."
She also told the council the bridge is "in a rough spot with the tide running right under it – that's hard on bridges." The city's condition assessment report calls this bridge the most significant structural concern in the system and notes that its rehabilitation is already in design.
The poor rating also matters for funding. It is what makes the bridge eligible for the federal program paying for the fix.
The money comes from the Highway Bridge Program. The Federal Highway Administration funds it, and Caltrans' Local Assistance Division administers it. Locally owned bridges can qualify for rehabilitation funding when the state finds them in poor condition and important for traffic movement. The city has been working toward this grant since 2019, and each step is in the public record:
| Date | Step |
|---|---|
| 2019 | City staff identify the bridge as a good candidate for Highway Bridge Program funding |
| June 24, 2020 | City Council authorizes staff to apply |
| October 24, 2022 | Caltrans adds the San Elijo Lagoon bridge rehabilitation to its program list |
| June 14, 2023 | Council appropriates $1,308,000 in grant funds and $150,000 in city matching funds |
| February 2025 | Federal certification of SANDAG's 2025 regional plan includes partial design funding |
| March 11, 2026 | Council awards a $199,817 design and permitting contract to Dokken Engineering |
| September 9, 2026 | Council receives the Kleinfelder bridge assessment |
In 2023, the city's staff report on the grant estimated the whole project at $17 million. The 2026 assessment puts Encinitas's local match for designing and building it at about $3.8 million. That is most of the roughly $5.9 million the city expects to spend over 10 years on its 46 bridges.
That match only covers repairs. Engineering Department Director Dan Nutter told the council that the hard question with Caltrans is what counts as "repair" and what counts as "betterment." According to the Union-Tribune, any major improvement falls under betterment, and Encinitas pays its full cost. Nutter's example was widening the narrow pedestrian walkway.
That puts the bridge's most-used walkway in the category with no grant money behind it. The west side, the ocean-view side, is the one people walk most and the narrower of the two.
Councilmember Joy Lyndes represents the Cardiff district that includes the bridge. She told the council that area residents will want betterments, given how many pedestrians and cyclists cross every day, and that it makes sense to do improvements alongside the repair work. "We're probably never going to have a better opportunity," she said, as the Union-Tribune reported.
Nutter said construction could be about five years away. "This is an arduous process," he told the council. The assessment's 10-year plan puts $3.42 million toward construction for the lagoon bridge in its fifth year. That is a planning figure, not a scheduled start.
Five years is a long time on a bridge you cross every day. The decision about the walkways comes much sooner. Under the March contract, Dokken Engineering's first job is to draw concept exhibits for Caltrans to approve as the grant scope. The rest of the design depends on Caltrans accepting that scope and on further funding authorization. Those exhibits will show what counts as repair and what Encinitas would have to pay for itself. Whatever the drawings show for the west walkway will shape what the bridge looks like after construction.
At the September 9 meeting, the council's action was to receive and file the assessment. It did not vote on scope or on any betterments. The question of how wide the ocean-side walkway gets is still open, and the city's full price for widening it will come out of the same design work now underway.
These are the public records that track the project, all available online:
The next sign of the walkway decision will be the concept exhibits for Caltrans scope approval, the first task in the Dokken contract the council approved on March 11, 2026.
At Sun Greene, I keep up with the Cardiff projects that shape the walks, rides and drives people take every day, and this bridge is one of them. If you'd like to talk through what the work on the lagoon crossing could mean for your corner of Cardiff, let's connect.
Stay up to date on the latest real estate trends.
Work with Sun Greene for expert guidance, local insight, and a seamless buying or selling experience across North County San Diego’s most sought-after coastal communities.